In the Overall Project Status, the last category to the right is the "Overdue Tasks" icon.
How does sharepoint determine if a Task is Overdue for this specific Icon. Here is what is happenning to me:
Current Date = 11/5/2008
Any Task with an End Date of 11/6/2008 - 12/31/2008 is fine.
However, this icon is showing a task as overdue if the date is 1/1/2009 - 11/4/2009 and NOT overdue if the date is 11/6/2009 - 12/31/2009?
The "Overdue Tasks" view is working as expected, it is showing only tasks with an End Date of Less than Current Date and not = to Complete. Why is the icon on the Dashboard working differently? Where is the setting for this icon located so I can change it?
Any help is greatly appreciated
Dave at MB
How does sharepoint determine if a Task is Overdue for this specific Icon. Here is what is happenning to me:
Current Date = 11/5/2008
Any Task with an End Date of 11/6/2008 - 12/31/2008 is fine.
However, this icon is showing a task as overdue if the date is 1/1/2009 - 11/4/2009 and NOT overdue if the date is 11/6/2009 - 12/31/2009?
The "Overdue Tasks" view is working as expected, it is showing only tasks with an End Date of Less than Current Date and not = to Complete. Why is the icon on the Dashboard working differently? Where is the setting for this icon located so I can change it?
Any help is greatly appreciated
Dave at MB